Earned Value Analysis
Материал из Management Framework
Earned Value Analysis - Анализ стоимости проекта с учетом освоенного объема / Управление заработанной стоимостью.
Пример рассчета
Hourly Rate = $100
PV = $800 ($100 * 8 hours)
AC = $1100 ($100 * 11 hours)
EV $734 (baseline of $800 * 91.7% complete) (NOTE % Complete Actual (below) to get the 91.7% )
BAC = $800 (8 hours Baselined Effort-hours * $100 Hourly Rate)
EAC = $1200 (1100 + 100)
VAC = -$400 ($800 - $1200 )
% Complete Planned = 100% ($800 PV / $800 BAC)
% Complete Actual = 91.7% ($1100 AC / $1200 EAC)
SV = -$100 ($700 EV - $800 PV)
SPI = 0.88 ($700 EV / $800 PV)
CV = -$400 ($700 EV - $1100 AC) indicating a cost overrun
CPI = 0.64 ($700 EV / $1100 AC) indicating over budget
Смотри также
- wikipedia.org - Earned value management
- NASA - EVM
- Department of Defense - Earned Value Management Implementation Guide
- Управление стоимостью проекта
- tutorialspoint.com - EVM
- najah.edu - evaslides
- PMI ,"Practice Standard For Earned Value Management"
- tutorialspoint.com - EVM Example - Пример использован выше в статье
- Пояснение EVA со скринами из MS Project
- MSP2003 - Applying earned value analysis to your project
- Earned Value Management Explained - хорошая короткая статья, есть ссылки на инструменты
- Почему EVA анализ не работает
Управление проектами - основные статьи:
- Методики управления проектами
- Проектный менеджмент
- Дисциплины управления проектами
- Процессы управления проектами
- Роли в проектном управлении
- Показатели проекта
- Документы в управлении проектами
- Терминология управления проектами
Категории базы знаний:
- Дисциплины - Бизнес анализ, Управление рисками, Управление качеством, Системный анализ, Менеджмент
- Инструменты - Процессы, Роли, Показатели, Документы, Термины, Информационные технологии, Метод
- Внешние ресурсы - Отраслевые стандарты, Книги, Полезные Web ссылки
- Отношения - Эксперты, Участники